This past week was a short one with Thanksgiving being in there and yet they still managed to make some pretty dramatic changes.

We’ve now got shutters on the exterior of the house.

Exterior with Shutters

They started installing the hood. It’s still missing the top molding.

Kitchen Hood

They’ve also been installing the hardwood floor. The upstairs is mostly finished and they were working  the downstairs when we visited.

Wood Floor

Hardwood Flooring

They’ve been working on preparing the master shower for tile for a while and now they’ve actually started laying the tile.

Master Bath Tile

Master Shower Floor Tile

While we were there, we also noticed they added some additional trim to the chair rail to make it more substantial looking.

Chair Rail

Finally, one little snag with the lights. I hate the look of amber glass so when we choose lights we specifically looked for white glass, however the fans that were installed had amber glass. We told Tommy and he’s working to fix it.

Fan with Amber Glass